What's coming: openings, roads and projects, with the dates

One page per thing that is opening, widening, being approved or still under construction. Every date is labelled actual or projected, every figure links to the agency, developer or owner that published it, and each page says when it was last re-checked. No forecasts of our own, no property-value claims.

Roads and bridges

Under construction Estero (Lee County)

Corkscrew Road widening, Phase 2: the completion date, the lanes and the new Alico Road signal (2027)

Lee County's Road Watch report for October 8 to 14, 2026 says Phase 2 completion is now expected in late spring 2027, because of additional Lee County Utilities work and delays in FPL and Lumen utility relocations. The county's August and September updates had said end of 2026, and the project website still says late 2026.

Next: Completion, projected late spring 2027 (Lee County Road Watch, October 8 to 14, 2026)

Sources re-checked Oct 15, 2026

Approved Marco Island and Goodland

Goodland Bridge (Stan Gober Memorial Bridge) repairs: the lane situation and the spring 2027 completion date

Collier County projects completion of the Stan Gober Memorial Bridge rehabilitation in spring 2027 under an $8.94 million contract with M&J Construction. The county's March 9, 2026 release said work would mobilize that week, with deck work and one-lane signalized traffic expected to be finished by summer 2026. A tourism site reported single-lane operation in late March. The county has published nothing since, so whether the bridge is one lane or two today is unverified.

Next: Whole rehabilitation complete, projected spring 2027 (county project page)

Sources re-checked Oct 15, 2026

Under construction East Naples

I-75 at Collier Boulevard (Exit 101): the flyovers, the ramp changes and a completion date FDOT gives two ways (2026 to 2027)

The interchange has been under construction since early 2023. FDOT's page, updated October 13, 2026, gives two projected completions: early 2027 in the project details and end of 2026 in its RoadWatch text. No flyover opening day has been published.

Next: Projected completion: end of 2026 or early 2027, depending on which FDOT field you read; weekly RoadWatch for closures

Sources re-checked Oct 15, 2026

Under construction North Naples to south Fort Myers along I-75

I-75 widening from Golden Gate Parkway to Alico Road: express lanes, the October hearings and what has a date (2026 to 2027)

FDOT lists the 21-mile corridor in its construction phase with a project start of mid 2026, and has scheduled public hearings on the auxiliary-lane work for October 27, 2026 in North Naples and October 28 online. Those hearings will not cover noise walls. No cost and no final completion date appear on FDOT's pages.

Next: Public hearings: Tuesday, October 27, 2026 in person (Vanderbilt Presbyterian Church, 1225 Piper Boulevard; open house 4 to 4:30 p.m., presentation 4:30 p.m.) and Wednesday, October 28, 2026 at 6 p.m. on Microsoft Teams

Sources re-checked Oct 15, 2026

In review North Naples

Pine Ridge Road jughandle at Livingston Road: what it is, where the design stands and the projected 2027 construction start

Collier County's 60 percent design handout, from the June 18, 2026 public meeting, projects design completion by the end of 2026 and says construction could begin in summer 2027 and last about 18 months. That is a design-stage projection: no construction contract has been awarded and no closure plan has been published.

Next: Design completion, projected by the end of 2026 per the county's June 2026 handout

Sources re-checked Oct 15, 2026

How these pages work

Actual, projected, unknown

Actual means it happened and a public record says so: a contract award, a ribbon cutting, a first day of class. Projected means the owner or agency forecast it on the date shown beside the source; forecasts move, and the page keeps the old date next to the new one when they do. Unknown means no source states it, so the page says so instead of guessing. Status words follow the public record: a project is "approved" when a board voted, "under construction" when the owner says work is under way, and "open" only when it has opened.

Each page lists the communities we cover in the same area or corridor. That is geography, not a measured drive time, and living near a project confers no right to anything it builds. For the fees, rules and amenities of those communities, start with the community guides, the fee matrix and the amenity matrix.

Tell me when something on this list changes

Pick what you care about and I will email you when a date moves, a store opens or a road reopens. Occasional, specific, and one click stops it.

Know about a project that should be on this list?

Send the official link and I will add it with its dates and sources.

Call Nick · (239) 877-4646 Book a call Realty ONE Group MVP

How would you like to reach us?

Realty ONE Group MVP The Nicholas Nolan Team · (239) 877-4646

Call from this computer Send us a message

Calling from this computer opens your calling app, such as FaceTime or Microsoft Teams. On your phone? Dial the number above.