Roads and bridges

Corkscrew Road widening, Phase 2: the completion date, the lanes and the new Alico Road signal (2027)

General education only — not legal, tax, financial, insurance, or other professional advice. Read the full disclaimer
Under construction Status as of October 8 to 14, 2026 (Lee County DOT Road Watch report)

Lee County's Road Watch report for October 8 to 14, 2026 says Phase 2 completion is now expected in late spring 2027, because of additional Lee County Utilities work and delays in FPL and Lumen utility relocations. The county's August and September updates had said end of 2026, and the project website still says late 2026.

Next milestone
Completion, projected late spring 2027 (Lee County Road Watch, October 8 to 14, 2026)
Where
Corkscrew Road from Bella Terra Boulevard to just east of Alico Road, Estero
Who is building it
Lee County Department of Transportation; contractor Bergeron Land Development, Inc.
We re-check this page
October 22, 2026, then monthly, or sooner if Lee County posts a Road Watch report with a new date

For anyone who lives off Corkscrew Road east of Ben Hill Griffin Parkway, the only question that matters is when the cones come out. The answer changed this month, and the project’s own website has not caught up.

What is confirmed

Lee County is widening Corkscrew Road in two phases. Phase 2, from Bella Terra Boulevard to just east of Alico Road, began construction in early 2024 and builds four travel lanes, a new traffic signal at the Alico Road intersection, a 10-foot shared-use path on the south side and a 6-foot sidewalk on the north side. The contractor is Bergeron Land Development, Inc., and the county puts the cost at approximately $27 million. The 4.4-mile figure you will see quoted is the length of the whole two-phase corridor from Ben Hill Griffin Parkway to Alico Road.

What is projected, and how it moved

Lee County’s Road Watch report for October 8 to 14, 2026 says completion is now expected in late spring 2027, citing additional work required by Lee County Utilities and delays in utility relocations by FPL and Lumen. That supersedes the county’s own August 14 and September 7 updates, both relayed by the Village of Estero, which said end of 2026. The project website still reads “late 2026.” This page keeps each date with its source, because the sequence (spring 2026, then end of 2026, then late spring 2027) is itself the useful fact.

What is unknown

No open-to-traffic day, no date for the Alico Road signal, and no statement on whether the shared-use path is usable yet. A separate Village of Estero shared-use-path project on the western section of Corkscrew Road shows up in the same Road Watch with its own date and cost; it is not Phase 2.

Where to look between our checks

The county’s weekly Road Watch is the primary record. When it prints a new date, this page will show it beside the old one.

Key dates

"Actual" is a date that has happened and is documented. "Projected" is the owner's or agency's forecast on the date shown in the source, not a promise. "Unknown" means no source states it; we do not guess.

EventDateBasisSource
Construction began Early 2024 Actual [2]
Lee County update: completion expected end of 2026 August 14 and September 7, 2026 (superseded) Projected [4]
Lee County Road Watch: completion expected late spring 2027 Report for October 8 to 14, 2026 Projected [1]
New Alico Road signal activated Unknown Unknown —
All four lanes open to traffic Unknown Unknown —

The numbers, with their sources

FigureValueSource
Travel lanes in Phase 2 Four [2]
New traffic signal At the Alico Road intersection [2]
Shared-use path 10 feet wide, south side [2]
Sidewalk 6 feet wide, north side [2]
Project cost Approximately $27 million [1]
Contractor Bergeron Land Development, Inc. [1]
The 4.4-mile figure Describes the whole two-phase corridor from Ben Hill Griffin Parkway to Alico Road, not Phase 2 alone [2]

Still unknown or in conflict

  • No open-to-traffic day has been published. 'Late spring 2027' is the county's forecast on the date of the report, and it has moved before: spring 2026 in older material, end of 2026 in August and September, late spring 2027 in October.
  • The project website (corkscrewroadwidening.com) still says late 2026 and carries a footer naming FDOT, although Lee County owns the project. Its construction page also keeps an obsolete early-2024 Phase 1 forecast lower on the page.
  • The hero banner on that site describes a corridor widening from four lanes to six; the Phase 2 segment itself is described in the body as four lanes. This page uses the body text.
  • A separate Village of Estero project, a shared-use path on Corkscrew Road from Ben Hill Griffin Parkway to Bella Terra, appears in the same Road Watch with an estimated early 2027 completion and a cost of about $23 million. It is not part of Phase 2.

Communities we cover near this

Named by area and corridor, not by measured distance. Living nearby confers no rights to anything described on this page.

Questions people ask

When will the Corkscrew Road widening be finished?

Lee County's Road Watch report for October 8 to 14, 2026 says Phase 2 completion is expected in late spring 2027. The county's August 14 and September 7 updates had said end of 2026, and the project website still says late 2026. The newest county statement governs this page; no exact opening day has been published.

Why was Corkscrew Road Phase 2 delayed?

The county's October Road Watch attributes the new date to additional work required by Lee County Utilities and delays in utility relocations by FPL and Lumen. The September 7 update had also cited utility work.

How many lanes will Corkscrew Road have?

Phase 2 builds four travel lanes between Bella Terra Boulevard and just east of Alico Road, with a 10-foot shared-use path on the south side and a 6-foot sidewalk on the north side, per the project site. The site's banner about widening to six lanes describes the corridor-level concept, not this segment.

Is the Corkscrew Road bike path open?

Unknown. No source read for this page states whether the shared-use path is open; the county's reports describe the overall project as still under construction.

Sources & further reading

  1. Roadwatch Update, October 8, 2026 to October 14, 2026 (PDF) — Lee County Department of Transportation, October 8 to 14, 2026
  2. Corkscrew Road Widening (project site) — Lee County project outreach site, undated page, read October 15, 2026
  3. Construction, Corkscrew Road Widening — Lee County project outreach site, undated page, read October 15, 2026
  4. Corkscrew Road Widening Phase 2 update from Lee County on September 7, 2026 — Village of Estero (agency post relaying Lee County), September 7, 2026
  5. Corkscrew Road Widening Phase 2 update from Lee County on August 14, 2026 — Village of Estero, August 14, 2026

Every date and figure above was read on the publisher's own page on October 15, 2026. A projected date is the publisher's forecast on that day; agencies revise them. If you find a newer official source, send it and this page will be corrected with the date.

Weighing a home near this project?

Tell me which communities you are comparing and I will lay out what is documented, what is projected and what is still unknown, with no pressure.

Call Nick · (239) 877-4646 Book a call Realty ONE Group MVP

How would you like to reach us?

Realty ONE Group MVP The Nicholas Nolan Team · (239) 877-4646

Call from this computer Send us a message

Calling from this computer opens your calling app, such as FaceTime or Microsoft Teams. On your phone? Dial the number above.