Roads and bridges

Goodland Bridge (Stan Gober Memorial Bridge) repairs: the lane situation and the spring 2027 completion date

General education only — not legal, tax, financial, insurance, or other professional advice. Read the full disclaimer
Approved Status as of March 9, 2026 (county release announcing mobilization); county project page read October 15, 2026

Collier County projects completion of the Stan Gober Memorial Bridge rehabilitation in spring 2027 under an $8.94 million contract with M&J Construction. The county's March 9, 2026 release said work would mobilize that week, with deck work and one-lane signalized traffic expected to be finished by summer 2026. A tourism site reported single-lane operation in late March. The county has published nothing since, so whether the bridge is one lane or two today is unverified.

Next milestone
Whole rehabilitation complete, projected spring 2027 (county project page)
Where
Stan Gober Memorial Bridge, State Road 92 (San Marco Road), the Goodland approach to Marco Island
Who is building it
Collier County Transportation Engineering (project manager listed as Felipe Baez); contractor M&J Construction
We re-check this page
October 22, 2026, by phone to Collier County Transportation Engineering, then March 1, 2027, or sooner if the county posts a traffic or completion update

The Stan Gober Memorial Bridge is the one way between Goodland and Marco Island, so “is it one lane today” is not an idle question. The honest answer, as of October 15, 2026, is that the county’s last word is from March. This page says so instead of guessing.

What is confirmed

Collier County awarded an $8.94 million contract to M&J Construction to rehabilitate the bridge on State Road 92, also known as San Marco Road. The county’s March 9, 2026 release announced that mobilization was planned for that week and explained the traffic plan for the deck work: one lane open, controlled by temporary signals at both ends. Its project page projects completion by spring 2027.

A tourism website reported on March 22, 2026 that work was under way and the bridge was operating as a single lane with signals at each end. That is a third-party observation, and it is the most recent dated description of traffic on the bridge that this page could find.

What is projected

The March release anticipated the deck work and its lane closures would be completed by summer 2026, with the whole rehabilitation finishing the following spring. The project page carries spring 2027 as the completion target.

What is unknown

Whether the deck phase ended on schedule, and therefore whether drivers meet a signal today. No county statement after March 9, 2026 turned up in the sources read. The county’s Transportation Engineering line, (239) 252-8192, is the direct route to the answer, and this page’s next check is that call.

For boaters

Nothing in the sources addresses vertical clearance or navigation during the repairs. Marine notices, not this page, govern that.

Key dates

"Actual" is a date that has happened and is documented. "Projected" is the owner's or agency's forecast on the date shown in the source, not a promise. "Unknown" means no source states it; we do not guess.

EventDateBasisSource
Mobilization Week of March 9, 2026, as planned in the county's release Projected [1]
Work observed under way, single lane with signals March 22, 2026, as reported by a tourism website, not by the county Actual [3]
Deck work requiring lane closures Anticipated to be completed by summer 2026, per the March release; completion not confirmed Projected [1]
Entire rehabilitation complete Spring 2027 (the March release says 'next spring'; the project page says 'by spring of 2027') Projected [2]
Current lane configuration (October 2026) Unknown Unknown —

The numbers, with their sources

FigureValueSource
Contract $8.94 million, awarded to M&J Construction [2]
Traffic plan during deck work One lane open, controlled by temporary signals at both ends [1]
Road State Road 92, also known as San Marco Road [1]

Still unknown or in conflict

  • Whether the deck work finished by summer 2026 as planned, and whether the bridge is operating with one lane or two today. No county statement dated after March 9, 2026 was found; the newest dated description is a tourism website from spring 2026.
  • The county release does not name the waterway the bridge crosses. A news report called it Smokehouse Bay; that is not repeated here without a county map.
  • Whether boats can pass under the bridge during repairs is not addressed in any source read.

Communities we cover near this

Named by area and corridor, not by measured distance. Living nearby confers no rights to anything described on this page.

  • Marco Island The bridge carries San Marco Road between Goodland and Marco Island

Questions people ask

Is the Goodland Bridge open?

Every source read for this page describes the bridge as open to traffic during the rehabilitation, with a plan for one lane controlled by signals at both ends during deck work. Whether it is one lane or two today is unverified: the county has not published an update since March 9, 2026. Collier County Transportation Engineering, (239) 252-8192, is the place to ask before relying on it.

When will the Stan Gober Bridge repairs be finished?

Collier County's project page projects completion by spring 2027; its March 2026 release said 'next spring.' The contract is $8.94 million with M&J Construction.

Why is the Goodland Bridge one lane?

The county's March 2026 release explained that deck work would require lane closures, with traffic reduced to one lane controlled by temporary signals at both ends, and that the deck work was expected to be done by summer 2026. Whether that phase has ended is not confirmed by any county source read for this page.

Sources & further reading

  1. Stan Gober Memorial Bridge Rehabilitation Project Starting Soon — Collier County, March 9, 2026
  2. Transportation Engineering Projects — Collier County, undated page, read October 15, 2026
  3. Stan Gober (Goodland) Bridge Rehabilitation — Visit Everglades City, March 22, 2026 (page metadata shows an April 16, 2026 update)

Every date and figure above was read on the publisher's own page on October 15, 2026. A projected date is the publisher's forecast on that day; agencies revise them. If you find a newer official source, send it and this page will be corrected with the date.

Weighing a home near this project?

Tell me which communities you are comparing and I will lay out what is documented, what is projected and what is still unknown, with no pressure.

Call Nick · (239) 877-4646 Book a call Realty ONE Group MVP

How would you like to reach us?

Realty ONE Group MVP The Nicholas Nolan Team · (239) 877-4646

Call from this computer Send us a message

Calling from this computer opens your calling app, such as FaceTime or Microsoft Teams. On your phone? Dial the number above.