I-75 at Collier Boulevard (Exit 101): the flyovers, the ramp changes and a completion date FDOT gives two ways (2026 to 2027)
General education only — not legal, tax, financial, insurance, or other professional advice. Read the full disclaimerThe interchange has been under construction since early 2023. FDOT's page, updated October 13, 2026, gives two projected completions: early 2027 in the project details and end of 2026 in its RoadWatch text. No flyover opening day has been published.
- Next milestone
- Projected completion: end of 2026 or early 2027, depending on which FDOT field you read; weekly RoadWatch for closures
- Where
- I-75 at State Road 951 (Collier Boulevard), from Business Circle South to City Gate Drive, East Naples
- Who is building it
- FDOT District One, project 425843-2
- We re-check this page
- October 22, 2026, then weekly via FDOT's RoadWatch, or sooner if FDOT reconciles its two completion dates or announces a flyover opening
The interchange at I-75 and Collier Boulevard has been a construction zone since early 2023, long enough that the question has shifted from “what are they building” to “when does it end.” FDOT’s answer is two answers, on the same page.
What is confirmed
FDOT project 425843-2 rebuilds the Exit 101 interchange with new flyover ramps over 1.3 miles between Business Circle South and City Gate Drive, at a construction cost of $97 million. FDOT’s page, which shows a last-updated date of October 13, 2026, describes a new loop ramp as open.
What is projected, twice
The same October 13 page lists completion as “early 2027” in its project details and “end of 2026” in the RoadWatch text embedded lower down. FDOT’s Collier County RoadWatch page also says end of 2026, with no date stamp. A local newsletter’s May 2026 explainer, the best consumer answer before this page, carried end of 2026 as well. One of these will turn out to be the live schedule; this page shows both with their source until FDOT says which.
What is unknown
The opening day of each flyover and the current contract completion date. Nightly ramp and lane closures are posted weekly by FDOT and are deliberately not copied here, because a closure list that is a week old is worse than none.
If you use this interchange daily
The communities listed below sit on the Collier Boulevard corridor south of the interchange. That is geography only; this page tracks the project’s dates and makes no claim about traffic or value for any of them.
Key dates
"Actual" is a date that has happened and is documented. "Projected" is the owner's or agency's forecast on the date shown in the source, not a promise. "Unknown" means no source states it; we do not guess.
| Event | Date | Basis | Source |
|---|---|---|---|
| Construction began | Early 2023 | Actual | [1] |
| New loop ramp open | Described as open in FDOT's RoadWatch text; opening day not published | Actual | [1] |
| Completion, per FDOT's project details field | Early 2027 | Projected | [1] |
| Completion, per FDOT's RoadWatch text on the same page | End of 2026 | Projected | [2] |
| Flyover ramps open | Unknown | Unknown | — |
The numbers, with their sources
Still unknown or in conflict
- Which completion date is current. FDOT's page updated October 13, 2026 says early 2027 in its details and end of 2026 in its RoadWatch text; the Collier County RoadWatch page says end of 2026 with no date stamp. Neither is chosen here.
- Opening days for each flyover ramp and the current contract completion date.
- Nightly ramp closures change weekly. They are not listed here; FDOT's RoadWatch is the place to check before a night drive.
Communities we cover near this
Named by area and corridor, not by measured distance. Living nearby confers no rights to anything described on this page.
- Azure at Hacienda Lakes Collier Boulevard corridor, south of I-75 Homes for sale →
- Esplanade at Hacienda Lakes Collier Boulevard corridor, south of I-75 Homes for sale →
- Winding Cypress Collier Boulevard corridor, south of I-75 Homes for sale →
Questions people ask
When will the I-75 and Collier Boulevard construction be finished?
FDOT's project page, updated October 13, 2026, says early 2027 in its project details and end of 2026 in the RoadWatch text on the same page. A May 2026 local newsletter said end of 2026. Until FDOT reconciles its two fields, this page shows both and treats neither as confirmed.
What is being built at I-75 exit 101?
A rebuild of the interchange at Collier Boulevard (State Road 951) with new flyover ramps, over 1.3 miles from Business Circle South to City Gate Drive, at a construction cost of $97 million per FDOT. Construction began in early 2023.
Is the new Collier Boulevard ramp open?
FDOT's RoadWatch text describes a new loop ramp as open. The opening days for the flyover ramps have not been published. For tonight's closures, check FDOT's Collier County RoadWatch; this page does not track nightly closures because they change weekly.