Roads and bridges

Pine Ridge Road jughandle at Livingston Road: what it is, where the design stands and the projected 2027 construction start

General education only — not legal, tax, financial, insurance, or other professional advice. Read the full disclaimer
In review Status as of June 18, 2026 public meeting at 60 percent design; county project page read October 15, 2026

Collier County's 60 percent design handout, from the June 18, 2026 public meeting, projects design completion by the end of 2026 and says construction could begin in summer 2027 and last about 18 months. That is a design-stage projection: no construction contract has been awarded and no closure plan has been published.

Next milestone
Design completion, projected by the end of 2026 per the county's June 2026 handout
Where
Pine Ridge Road from Livingston Road east to Lawson Way, with the jughandle at the Pine Ridge Road and Livingston Road intersection
Who is building it
Collier County Transportation Engineering (project manager listed as Dennis McCoy, P.E.)
We re-check this page
December 1, 2026, then March 1, 2027, or sooner if the county posts final design plans, a bid or a contract award

Pine Ridge Road is carrying two construction clocks at once, and most of the confusion about the jughandle comes from mixing them up. FDOT’s diverging diamond at the I-75 interchange is under construction. The county’s jughandle at Livingston Road is still being designed. This page is about the second one.

What is confirmed

Collier County held a public information meeting on June 18, 2026 to show 60 percent design plans for the corridor from Livingston Road east to Lawson Way. The June 5 meeting notice describes the scope: a jughandle at the Pine Ridge Road and Livingston Road intersection, with turn-lane and sidewalk improvements along the corridor. The county’s project list carries it as the Pine Ridge Rd and Livingston Rd Intersection Improvements, with Dennis McCoy, P.E., as project manager.

What is projected

The two-page handout from that meeting is where the schedule lives, and it is the detail most summaries miss. It projects design completion by the end of 2026 and says construction could potentially begin in summer 2027, lasting approximately 18 months. The handout also proposes a second left-turn lane from Kramer Drive onto Pine Ridge Road.

Two cautions. The handout prints no issue date; its file metadata dates it to mid-June 2026, so “the end of this year” is read as the end of 2026. And a design team’s “potentially summer 2027” is not an approved construction start. The Board of County Commissioners has not awarded a contract, and no bid date has been published.

What is unknown

Cost, the award date, the final completion date and the maintenance-of-traffic plan during construction are not in any source read for this page. When the county publishes final plans or a bid, this page will carry the dates with their source.

Why it matters if you live on the corridor

Livingston Road and Pine Ridge Road are the way in and out for several communities we cover, and an 18-month construction window changes daily driving. This page tracks the schedule only. It makes no claim about what the project means for any home’s value, and it will not.

Key dates

"Actual" is a date that has happened and is documented. "Projected" is the owner's or agency's forecast on the date shown in the source, not a promise. "Unknown" means no source states it; we do not guess.

EventDateBasisSource
Public information meeting at 60 percent design June 18, 2026 Actual [3]
Design completion By the end of 2026 (the handout says 'by the end of this year' and dates from June 2026) Projected [2]
Construction start Summer 2027, described as 'potentially' commencing Projected [2]
Construction duration Approximately 18 months Projected [2]
Board approval of a construction contract Unknown Unknown —
Open to traffic in final configuration Unknown Unknown —

The numbers, with their sources

FigureValueSource
Design stage at the June 2026 meeting 60 percent [2]
Project limits Livingston Road to Lawson Way [3]
Kramer Drive A second left-turn lane onto Pine Ridge Road is proposed [2]
Construction cost Unknown; not published in the sources read —

Still unknown or in conflict

  • The county's project list names this the Pine Ridge Rd and Livingston Rd Intersection Improvements; the handout and the June 5 meeting notice describe a corridor project to Lawson Way. Same project, two names.
  • The handout prints no issue date. Its schedule says 'by the end of this year'; the file's own metadata dates it to June 2026, so that is read as the end of 2026.
  • No budget, bid date, contract award or closure plan has been published. 'Summer 2027' is the design team's wording that construction could potentially begin then.
  • This is a separate project from the FDOT diverging diamond interchange at Pine Ridge Road and I-75 (FDOT project 445296-1). Do not read one project's dates as the other's.

Communities we cover near this

Named by area and corridor, not by measured distance. Living nearby confers no rights to anything described on this page.

Questions people ask

What is a jughandle?

A jughandle moves a left turn off the main intersection: instead of turning left across oncoming traffic, drivers leave the road by a ramp-style turn on the right and cross at a signal. Collier County's June 2026 handout and meeting notice describe a jughandle at the Pine Ridge Road and Livingston Road intersection, with turn-lane and sidewalk improvements east to Lawson Way. The handout has the drawings.

When will construction on the Pine Ridge Road jughandle start?

The county's 60 percent design handout from June 2026 projects design completion by the end of 2026 and says construction could potentially begin in summer 2027 and last about 18 months. No construction contract has been awarded, and the county has not published a bid or award date, so this is a projection from the design stage.

Is this the same project as the I-75 interchange construction at Pine Ridge Road?

No. The interchange work at I-75 is an FDOT project (445296-1), a diverging diamond interchange that is under construction. The jughandle at Livingston Road is a Collier County project still in design. They are on the same road but have different owners, schedules and sources.

Sources & further reading

  1. Transportation Engineering Projects — Collier County, undated page, read October 15, 2026
  2. Pine Ridge Road Corridor Improvements Project, 60 Percent Design Plans handout (PDF) — Collier County, June 2026 (no printed date; file metadata June 15 to 19, 2026)
  3. Public Info Meeting: Pine Ridge Road Corridor Project — Collier County, June 5, 2026
  4. FDOT project 445296-1, I-75 at Pine Ridge Road (diverging diamond interchange) — FDOT District One, FDOT project page; see it for that project's current dates

Every date and figure above was read on the publisher's own page on October 15, 2026. A projected date is the publisher's forecast on that day; agencies revise them. If you find a newer official source, send it and this page will be corrected with the date.

Weighing a home near this project?

Tell me which communities you are comparing and I will lay out what is documented, what is projected and what is still unknown, with no pressure.

Call Nick · (239) 877-4646 Book a call Realty ONE Group MVP

How would you like to reach us?

Realty ONE Group MVP The Nicholas Nolan Team · (239) 877-4646

Call from this computer Send us a message

Calling from this computer opens your calling app, such as FaceTime or Microsoft Teams. On your phone? Dial the number above.